sharepoint 2010 - calculate days excluding weekends in sharepoint2010 -


how exclude weekends(sat , sun) when counting number of days between start , end time in sharepoint 2010 calculate column.

1.i have calender added sharepint 2010 , there 2 columns start time , end time , requirement calculate number of days between star time , end time excluding weekends(sat , sun) means calculate working days only. tried

=if(and((weekday(enddate,2))<(weekday(startdate,2)),((weekday(startdate,2))-(weekday(enddate,2)))>1),(((datedif(startdate,enddate,"d")+1))-(floor((datedif(startdate,enddate,"d")+1)/7,1)*2)-2),(((datedif(startdate,enddate,"d")+1))-(floor((datedif(startdate,enddate,"d")+1)/7,1)*2))) 

also,

=(datedif([startdate],[enddate],"d"))-int(datedif([startdate],[enddate],"d")/7)*2-if((weekday([enddate])-weekday([startdate]))>0,2,0)+1 

but not getting correct out put.

thanks

=if(and((weekday(enddate,2))<(weekday(startdate,2)),((weekday(startdate,2))-(weekday(enddate,2)))>1),(((datedif(startdate,enddate,"d")+1))-(floor((datedif(startdate,enddate,"d")+1)/7,1)*2)-2),(((datedif(startdate,enddate,"d")+1))-(floor((datedif(startdate,enddate,"d")+1)/7,1)*2))) 

this should trick :)